Hours: 53:30

Date User Activity Issue Comment Hours
04/21/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-04-24T05:22:08.816Z: 3h-(3.0)h spend at: 2025-04-21 3:00 Actions
04/14/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-04-15T11:06:02.884Z: 3h-(3.0)h spend at: 2025-04-14 3:00 Actions
04/13/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-04-14T08:00:40.087Z: 3h 30m-(3.5)h spend at: 2025-04-13 3:30 Actions
04/01/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-04-03T05:53:58.817Z: 1h-(1.0)h spend at: 2025-04-01 1:00 Actions
03/16/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-03-17T06:58:39.736Z: 2h-(2.0)h spend at: 2025-03-16 2:00 Actions
03/16/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-03-19T11:44:57.368Z: 2d-(16.0)h spend at: 2025-03-16 16:00 Actions
01/31/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-01-31T07:33:35.468Z: 2h-(2.0)h spend at: 2025-01-31 2:00 Actions
01/30/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-01-31T05:32:35.141Z: 1h-(1.0)h spend at: 2025-01-30 1:00 Actions
01/30/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-01-31T10:59:18.352Z: 1h-(1.0)h spend at: 2025-01-30 1:00 Actions
01/29/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-01-31T05:32:07.307Z: 7h-(7.0)h spend at: 2025-01-29 7:00 Actions
01/27/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-01-31T05:31:02.800Z: 7h-(7.0)h spend at: 2025-01-27 7:00 Actions
01/26/2025 Redmine Admin Development Task #16359: CCS Integration implementation phase Capture & Consume Imported from GitLab by @Vikram Jhurry on 2025-01-31T05:30:15.730Z: 7h-(7.0)h spend at: 2025-01-26 7:00 Actions