Actions
Task #19620
openTask #19293: 2026 🛠️ Internal Support & Mentorship
VPN fortinet update with IT team
Status:
New
Priority:
Normal
Assignee:
-
Start date:
03/30/2026
Due date:
03/30/2026 (about 5 months late)
% Done:
0%
Estimated time:
0:00 h
Spent time:
GitLab ID:
4103
GitLab Milestone:
GitLab Ticket Number:
165
GitLab Time Logged:
3600
Lock Timeline Date:
No
gitlab project trace:
2026 🛠️ Internal Support & Mentorship
GitLab Sync Log
[{"id": "41290", "author": "Nihaal Ramfoll", "hours": 1.0, "created": "2026-03-30T11:01:34.901Z", "log_date": "2026-03-16", "comment": "Imported from GitLab by @Nihaal Ramfoll on 2026-03-30T11:01:34.901Z: 1h-(1.0)h spend at: 2026-03-16", "status": "active", "deleted_by": "", "redmine_entry_id": 12821}]