Actions
Task #18570
openTask #18634: Sprint Planning for 25/08/2025 - 05/09/2025
Vessel schedule_Bring Vessel information_For Already approved vessel on CCS to FFS.
Status:
QA
Priority:
Normal
Assignee:
-
Start date:
07/30/2025
Due date:
08/22/2025 (about 4 months late)
% Done:
0%
Estimated time:
0:00 h
GitLab ID:
3033
GitLab Milestone:
GitLab Ticket Number:
794
GitLab Time Logged:
0
Lock Timeline Date:
No
gitlab project trace:
Sprint Planning for 25/08/2025 - 05/09/2025
Description
Further to discussion with the stakeholder, below has been discussed.
In the event that a vessel has already been approved at Custom (on CCS). The FFS system should be able to capture a minimum of information upon inserting the ATP number on FFS.
This will minimize manual data input on the System.
Do you require any additional information, please let me know.