Actions
Task #18492
closedTask #18500: Ocean Sprint Planning for 17/07/2025 - 25/07/2025
PDF Reports post meeting EDL - Sales/Cost Sheet
Status:
Closed
Priority:
High
Assignee:
-
Start date:
07/14/2025
Due date:
07/25/2025
% Done:
100%
Estimated time:
0:00 h
GitLab ID:
2957
GitLab Milestone:
GitLab Ticket Number:
740
GitLab Time Logged:
0
Lock Timeline Date:
No
gitlab project trace:
Ocean Sprint Planning for 17/07/2025 - 25/07/2025
Description
Module: Ocean Export & Import
- The user should be able to print the Sales/Cost Sheet at any time once an HBL is saved in the system.
- The user should have the option to "Send via Mail" or WhatsApp as well.
- System logs who generated and sent the booking confirmation and when.
- The report should be available on the File reference list at the master level.
Refer to the below sample report provided by EDL.
GitLab Sync Log
[]
Actions