Task #18387

open

Task #19100: Sprint Planning for 17/11/2025 - 28/11/2025

Post Training EDL/WSC 19/06/25: Client - Single client but different payment terms

Added by Redmine Admin 6 months ago. Updated about 2 hours ago.

Status:
New
Priority:
High
Assignee:
-
Start date:
06/19/2025
Due date:
06/19/2025 (about 6 months late)
% Done:

0%

Estimated time:
8:00 h
GitLab ID:
2836
GitLab Milestone:
GitLab Ticket Number:
680
GitLab Time Logged:
0
Lock Timeline Date:
No
gitlab project trace:
Sprint Planning for 17/11/2025 - 28/11/2025

Description

As pointed out by EDL and WSC during training on 19/06/2025, A single client (identified by the unique Client Code) can have different payment terms per business type:

"Cash" Client for Import transactions

"Credit" Client for Export transactions

image.png{width=441 height=232}

As discussed, Applicable for both Sea and Air.

@noyan_avisham @nayeck_nadeem As agreed, kindly update ticket as per how you will develop this functionality.


GitLab Sync Log

[]

Actions #1

Updated by Redmine Admin 6 months ago

  • GitLab Sync Log updated (diff)
Actions #2

Updated by Redmine Admin 5 months ago

  • Parent task set to #18453
  • gitlab project trace set to Ocean Sprint Planning for 01/07/2025 - 11/07/2025
Actions #3

Updated by Redmine Admin 5 months ago

  • Due date changed from 06/19/2025 to 07/11/2025
  • Estimated time changed from 0:00 h to 8:00 h
Actions #4

Updated by Redmine Admin 2 months ago

  • Parent task changed from #18453 to #18862
  • gitlab project trace changed from Ocean Sprint Planning for 01/07/2025 - 11/07/2025 to Sprint Planning for 06/10/2025 - 17/10/2025
Actions #5

Updated by Redmine Admin 2 months ago

  • Due date changed from 07/11/2025 to 06/19/2025
  • Parent task changed from #18862 to #18880
  • gitlab project trace changed from Sprint Planning for 06/10/2025 - 17/10/2025 to Sprint Planning for 20/10/2025 - 31/10/2025
Actions #6

Updated by Redmine Admin about 2 months ago

  • gitlab project trace deleted (Sprint Planning for 20/10/2025 - 31/10/2025)
Actions #7

Updated by Redmine Admin 23 days ago

  • Parent task changed from #18880 to #19100
  • gitlab project trace set to Sprint Planning for 17/11/2025 - 28/11/2025