Actions
Task #18657
openTask #19002: Sprint Planning for 03/11/2025 - 14/11/2025
Automation - Vessel Schedule
Status:
New
Priority:
Normal
Assignee:
-
Start date:
08/21/2025
Due date:
08/21/2025 (about 4 months late)
% Done:
12%
Estimated time:
40:00 h
Spent time:
GitLab ID:
3130
GitLab Milestone:
GitLab Ticket Number:
856
GitLab Time Logged:
18000
Lock Timeline Date:
No
gitlab project trace:
Sprint Planning for 03/11/2025 - 14/11/2025
Description
- Create/update Import Schedule
- Upload Notice of Arrival - NOA
- Retrieve and check the NOA again
- Create/update Export Schedule
- Add/update Deadline Dates
- Check reminder mails (depends on how many days you have put the “Notify” reminder)
- Try to delete a vessel schedule which is already attached to a file ref, quotation or shipment cost.
GitLab Sync Log
[{"id": "34012", "author": "Yashvee Seetul", "hours": 5.0, "created": "2025-11-17T10:16:12.245Z", "log_date": "2025-11-16", "comment": "Imported from GitLab by @Yashvee Seetul on 2025-11-17T10:16:12.245Z: 5h-(5.0)h spend at: 2025-11-16", "status": "active", "deleted_by": "", "redmine_entry_id": 11278}]
Updated by Redmine Admin 3 months ago
- Estimated time changed from 0:00 h to 40:00 h
Updated by Redmine Admin about 1 month ago
- Parent task set to #19002
- gitlab project trace set to Sprint Planning for 03/11/2025 - 14/11/2025
Updated by Redmine Admin 23 days ago
- % Done changed from 0 to 12
- GitLab Time Logged changed from 0 to 18000